Citizens’ groups ask Federal Court to review the decision to license a giant aboveground radioactive waste facility beside the Ottawa River

February 8, 2024

le français suit

For immediate release

(Ottawa, February 8, 2024) –  Concerned Citizens of Renfrew County and Area, Ralliement contre la pollution radioactive and the Canadian Coalition for Nuclear Responsibility have launched a legal challenge to the recent decision by the Canadian Nuclear Safety Commission (CNSC) to license the construction of a giant radioactive waste mound beside the Ottawa River, 180 km north-west of Ottawa. The giant mound is known as the “Near Surface Disposal Facility” or “NSDF.”

The three groups are asking the Federal Court to review the Commission’s failure to adequately consider the following evidence:

  • Radiation doses from the NSDF (as estimated by the proponent) would exceed some limits prescribed by Canadian regulations and international standards;
  • The proponent, Canadian Nuclear Laboratories (CNL), did not provide sufficient information about the waste that would go into the NSDF thereby rendering its Safety Case unreliable;
  • A key document submitted by CNL, the “Waste Acceptance Criteria,” includes an override section that would allow CNL to dispose of waste in the NSDF that does not meet the acceptance criteria. The override section nullifies any guarantees that only acceptable waste would be put in the mound and it makes the Safety Case a fiction;
  • Waste verification processes are inadequate to ensure that waste going into the NSDF meets Waste Acceptance Criteria;
  • CNL failed to provide information about many other projects it is undertaking on the same property that are likely to contribute to cumulative environmental impacts of the radioactive waste mound; 
  • CNL proposed as a mitigation measure* to run a pipeline into Perch Lake, which would actually increase the flow of radioactive tritium into the Ottawa River, rather than decreasing it; and
  • Habitat and residences of protected species would be destroyed by site preparation and construction of the NSDF.

The application for judicial review submitted to Federal Court on Wednesday, February 7, also submits that the CNSC decision is unreasonable because the Commission did not issue a licence to prepare a site, or conduct the necessary assessment in relation to site preparation. 

“In our view, the Commission’s decision to license the giant radioactive waste mound, one kilometer from the Ottawa River, is a serious mistake,” said Lynn Jones of the Concerned Citizens of Renfrew County and Area. “The mound is designed to last only 550 years, while much of the waste that would go into it will remain hazardous and radioactive for thousands of years.”

Represented by Nicholas Pope of Hameed Law, the applicants are seeking an order quashing the decision to amend the license to allow for construction of the NSDF. 

– 30 –

* Mitigation measures are supposed to eliminate, reduce or control an adverse effect that the project would cause. 

~~~~~~

Background

Ten Things Canadians need to know about the giant radioactive waste mound coming to the Ottawa River 

Concerned Citizens of Renfrew County and Area is a citizens’ group that advocates for prevention and clean-up of radioactive pollution from nuclear facilities in the Ottawa Valley. 

The Canadian Coalition for Nuclear Responsibility is a non-profit organization that conducts education and research on issues related to nuclear energy.

Ralliement contre la pollution radioactive is an association that promotes responsible solutions for managing radioactive waste to reduce risks to the environment and to public health.

~~~~~~~~~~~~~~~~~~

Des groupes de citoyens demandent à la Cour fédérale de réviser la décision d’autoriser un dépôt de déchets radioactifs en surface près de la rivière des Outaouais.

(Ottawa, le 8 février 2024) – Concerned Citizens of Renfrew County and Area, le Ralliement contre la pollution radioactive et le Regroupement pour la surveillance du nucléaire ont demandé hier la révision judiciaire d’une décision de la Commission canadienne de sûreté nucléaire (CCSN). Celle-ci a récemment autorisé la construction d’une installation géante de gestion des déchets radioactifs près de la surface (IGDPS), tout près de la rivière des Outaouais à 180 km d’Ottawa.

Les trois groupes reprochent à la Commission de sûreté nucléaire d’avoir autorisé cette décharge radioactive sans considérer plusieurs éléments essentiels :

• Les doses de rayonnement annoncées par le promoteur de cette installation dépasseront certaines limites prescrites par la réglementation canadienne et les normes internationales ;

• Le promoteur, les Laboratoires Nucléaires Canadiens (LNC), n’a pas fourni suffisamment de renseignements sur les déchets qui seront placés dans cette installation, si bien que son dossier de sûreté n’est pas fiable ;

• Un document-clé soumis par les LNC, intitulé Les critères d’acceptation des déchets, inclut une section de dérogation qui permettra de placer dans cette IGDPS des déchets plus dangereux que ne le permettent les critères d’acceptation officiels. Cette possibilité de dérogation rend illusoire toute garantie de sécurité;

• Les processus prévus ne permettront pas de garantir que les déchets placés dans l’IGDPS sont conformes aux critères d’acceptation;

• Les LNC ont omis de fournir des informations sur plusieurs autres projets voisins dont les impacts environnementaux s’ajoutent à ceux des déchets placés dans l’IGDPS;

• Les LNC ont proposé comme mesure d’atténuation* d’installer un pipeline de déversement vers le lac Perch voisin, ce qui augmentera les rejets de tritium radioactif dans la rivière des Outaouais plutôt que de les diminuer ;

• L’habitat et les abris de plusieurs espèces protégées seront détruits par la préparation du site et la construction de l’IGDPS.

Selon cette demande de contestation judiciaire présentée à la Cour fédérale le 7 février, la décision de la CCSN est aussi déraisonnable parce que la Commission n’a pas émis de permis pour préparer l’emplacement et n’a pas procédé à l’évaluation nécessaire avant cette préparation de l’emplacement.

« À notre avis, la Commission commet une grave erreur en autorisant cette installation géante de gestion des déchets radioactifs à un kilomètre de la rivière des Outaouais», a déclaré Lynn Jones, de Concerned Citizens of Renfrew County and Area. « L’IGDPS durera à peine 550 ans alors qu’une grande partie des déchets qui y seront placés resteront dangereux et radioactifs pendant des milliers d’années. »

Les demandeurs sont représentés par Nicholas Pope de Hameed Law. Ils demandent une ordonnance qui obligera la CCSN à réévaluer sa décision de modifier le permis pour permettre la construction de l’IGDPS.

-30-

*Les mesures d’atténuation ont pour but d’éliminer, réduire ou contrôler un effet négatif du projet.

Contexte

Dix choses que les Canadiens doivent savoir sur le monticulede déchets radioactifs en bordure de la rivière des Outaouais

Concerned Citizens of Renfrew County and Area est un groupe de citoyens qui prône la prévention et l’assainissement de la pollution radioactive provenant des installations nucléaires de la vallée de l’Outaouais.

Le Regroupement pour la surveillance du nucléaire est une organisation à but non lucratif qui mène des activités d’éducation et de recherche sur les questions liées à l’énergie nucléaire.

Le Ralliement contre la pollution radioactive est une association qui promeut des solutions responsables pour la gestion des déchets radioactifs, afin de réduire les risques pour l’environnement et la santé publique.

Flaws and deficiencies in the CNSC-led Environmental Assessment for the NSDF

June 29, 2023

The seven year long, CNSC-led, Environmental Assessment of the proposed giant radioactive waste mound or “NSDF” has been fraught with serious problems and deficiencies.  These deficiencies, in our view, have led to a poor-quality assessment, leaving the Commission with poor recommendations on which to base its EA decision.

Inadequate consultation with Indigenous Peoples on whose unceded territory the proposed radioactive dump would be built

CNSC and the proponent announced the design, site and commencement of an EA for the dump in 2016. No consultation with Algonquin First Nations occurred prior to the announcement of the design, site and EA. Some consultations occurred during the protracted EA, but not all Algonquin First Nations were consulted. As a seeming afterthought, after the final NSDF licensing hearing concluded in June 2022, the CNSC decided to leave the record open for further consultations with two of the eleven Algonquin First Nations whose peoples have lived in the Ottawa River watershed since time immemorial, and whose people never ceded their territory to the Crown via a treaty.

Problems in the early stages with the project description and scoping for the EA

1 The CNSC dismissed critical comments on the project description, submitted by radioactive waste management experts, that should have resulted in a fundamental rethinking of the project design, or at least major changes to the scope of the Environmental Assessment.

2  The CNSC’s scoping of the Near Surface Disposal Project (NSDF) was seriously flawed. A combined scoping decision for three separate projects (the NSDF, and the entombment of the NPD and WR-1 reactors) was made nine days before the draft environmental impact statement (EIS) for the NSDF project was released. The CNSC allowed the proponent to conduct environmental impact studies before the project scope was determined. The scoping decision ignored many serious criticisms of the NSDF project description. It was released by a 1-person “Panel” comprised solely of the CNSC President. The public was not apprised of the “Panel” hearing, which may never have actually taken place.

Obstacles to “meaningful public participation”

3  The CNSC did not require the NSDF proponent to translate documents into French, despite a clear potential for adverse environmental impacts in the Province of Quebec. The closest residents to the NSDF project site are in Quebec. Lack of access to French language documents led to a complaint from a Quebec citizen and a decision by the Commissioner of Official Languages to require translation of the draft EIS.

4  The CNSC delayed or refused to provide access to documents referenced in the draft EIS for the Near Surface Disposal Project. A footnote on page 3-14 of the draft EIS (12) states that “The Safety Analysis Report demonstrates that even after failure of some of the design features, the wastes do not present a risk to the public and environment.” However, the Safety Analysis Report was not released until after the public comment period on the draft EIS ended. Key portions of this document (such as section 4.2.1.3 on “Nuclear Criticality Safety”) were redacted.

5  The CNSC did not provide the “meaningful opportunities for public participation” required by section 4(1)(e) of CEAA 2012.  CNSC closed  the record for public comments pursuant to the Environmental Assessment in August 2017 following CNL’s release of a draft Environmental Impact Statement.  This created nearly a 5-year gap before the May/June 2022 hearing.  CNSC provided no opportunity for the public to provide formally recorded comments on the final EIS, despite the numerous changes made to the project that are reflected in it.

6 The CNSC arbitrarily decided that written intervenors at the May/June 2022 hearing would not have the right to make final submissions.

7  The CNSC’s January 31, 2023 Notice of Public Hearing and Procedural Guidance for Final Submissions said that “new information may not be presented.”  This was changed very close to the submission deadline (on May 17, 2023) to “Final submissions may reference any material on the record.”

8  The CNSC public hearings provided no opportunity for witnesses to be cross-examined.

9 During public hearings, the proponent (CNL), its contractor (AECL) and the regulator (CNSC) were given unlimited time to make their arguments, but intervenors (other than First Nations) were restricted to 10 minute presentations. In some cases this required thousands of hours of research to be summarized in 10 minutes.

10 The document registry for the NSDF EA was very cumbersome and awkward and did not facilitate access to submissions by all interested parties.

CNSC staff recommendations to Commissioners fail to mention that the Commission is required to refer the decision to Cabinet if the project is likely to cause significant adverse environmental effects 

12 There is no mention of CEAA 2012 Section 52 in CMD 22-H7.  In this document CNSC staff recommend that the Commission decide that the NSDF is not likely to cause significant adverse environmental effects.  However, Section 52 says the Commission could decide that the NSDF is likely to cause significant adverse environmental effects; in which case the Commission must refer the matter to the Governor in Council (Cabinet).  Were CNSC staff so certain that the Commission would never dare to disagree with one of their recommendations that they felt it was not worth mentioning this option?  Regardless, this is a serious omission.  Information provided in CMD 22-H7 about “matters of regulatory interest” with respect to the proposed NSDF should be complete and objective.

CNSC staff allowed the proponent to write its own conditions (856 “mitigation measures”) and the manner in which they are written makes them impossible to enforce.

13. Section 53 of CEAA 2012 says that it is the decision maker — either the Commission or Cabinet  and not the proponent – that “must establish the conditions… that would permit a designated project to be carried out.”  However, CNSC staff allowed the proponent to write its own conditions (the 856 mitigation measures in CNL’s 105-page NSDF Consolidated Commitments List) in a manner that they would be impossible to enforce. There is no evidence that the Commission ever reviewed these conditions.  Furthermore, the CNSC staff draft licence handbook for the NSDF Project requires CNL to only implement mitigation measures during construction and pre-operation activities. Most of the significant adverse impacts of the NSDF Project would occur in the operation and post-closure phases. By only requiring mitigation of adverse effects occurring during construction and pre-operation activities, the CNSC’s approach would not mitigate the most significant adverse impacts of the NSDF Project.

“With regard to section 53, it is astounding that the CNSC has allowed the proponent, CNL, to write its own mitigation measures, and to write them in such a way that nearly all of them would be unverifiable.”

Ole Hendrickson, CCRCA researcher

Problems with the “Administrative Protocol” document

The “Administrative Protocol” is a document co-signed by the regulator and the proponent. It described the steps to be followed for the Environmental Assessment with milestones and target dates. 

Six different versions of Appendix A to the Protocol were published between 2016 and 2022.

The Administrative Protocol omitted any mention of the Duty to Consult with First Nations

At one point in the middle of the EA process all the dates for milestones were removed.  Interested parties were left with no idea when they might be required to allocate time to preparing final briefs and oral presentations.

An original provision for a dedicated Environmental Assessment hearing was removed. No Environmental Assessment hearing was ever held. The Environmental Assessment report was buried in a staff document and contained no references whatsoever.

And finally…

The CNSC, as responsible authority, was unable to complete the Environmental Assessment in a “timely manner” as required by section 4(1)(f) of CEAA 2012.

EAs normally are completed within one or two years. The EA of the NSDF is currently in its seventh year and counting.

Should the CNSC be responsible for environmental assessment?

The Expert Panel on Reform of Environmental Assessment recommended in its final report to the Minister of Environment and Climate Change in 2017 that the CNSC not be in charge of Environmental or Impact Assessments. The CNSC-led EA of the NSDF proposal was started before the Expert Panel review so it was conducted previous legislation, but the flaws and failings documented above seem to suggest that removing the CNSC from involvement in Impact Assessment would be prudent.

Photo below by Robert Del Tredici, August 2018, Ottawa

Questions about Canada’s seventh report to the Joint Convention ~ letter to IAEA from CCRCA

From: Concerned Citizens of Renfrew County and Area

To: Rafael Mariano Grossi

Director General

International Atomic Energy Agency

Date: May 31, 2021

We thank the IAEA for organizing the September 2019 Integrated Regulatory Review Service (IRRS) Mission to Canada.Recommendation R1 in the report of this Mission is that ““The Government should enhance the existing policy and establish the associated strategy to give effect to the principles stated in the Canadian Radioactive Waste Management Policy Framework.”  

This is a still work in progress, as illustrated by Canada’s Seventh National Report to the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management.  As appropriate, we would be grateful if you could forward this note to participants in the 7th review meeting of the Joint Convention.

Article 32 of the Joint Convention says:

2. This report shall also include…  (iv) an inventory of radioactive waste that is subject to this Convention that: (a) is being held in storage at radioactive waste management and nuclear fuel cycle facilities; (b) has been disposed of; or (c) has resulted from past practices. This inventory shall contain a description of the material and other appropriate information available, such as volume or mass, activity and specific radionuclides;

Canada’s 7th report says that data are “not available” (N/A) for activity and specific radionuclides in the Government of Canada’s waste at the Chalk River Laboratories (CRL).  This is where most federal radioactive waste is stored and is Canada’s only facility for commercial radioactive waste storage. CRL is managed by “Canadian Nuclear Laboratories”, a private company owned by a consortium of multinational engineering firms under a 2015 contract with Atomic Energy of Canada Limited (AECL).

Canada’s 7th report omits considerable data shown in Table B-2 (appended below) of AECL’s 2014 Comprehensive Preliminary Decommissioning Plan, as well as additional data listed as “available” but not shown in Table B-2.  

Table B-2 provides activity values of 1040 TBq beta/gamma, 2.1 TBq alpha, 1070 TBq tritium, and ~ 75 TBq unspecified for a portion of the Chalk River wastes.  Data gaps in Table B-2 include CRL’s  oldest Waste Management Area, WMA A, and one of its newest, WMA H, where the Shielded Modular Above-Ground Storage (SMAGS) facilities are found.  Despite the data gaps in Table B-2, the activity and radionuclide data found therein should be included in Table D.8 of Canada’s 7th report.  

Table B-2 also lists additional activity data as being “AVAILABLE” for certain CRL waste areas, including the WMA B circular concrete bunkers, rectangular concrete bunkers, and tile holes; the WMA C extension unlined trenches; the potentially contaminated equipment, materials and drummed liquids in WMA D; and the reprocessing wastes in the Thorium Pit from operation of the 233U extraction facility.  

These data should also be reported pursuant to Article 32 of the Joint Convention.

There are major differences between the waste volume data for CRL in Canada’s 7th report and in Table B-2.  Table B-2 shows a total volume of all waste types of 235,165 m3, with an additional 380,000 m3 of contaminated soils and slags.  These are far higher values than those in Table D.8 of Canada’s 7th report.  It gives a total of only 154,858 m3 of all waste types, and only 156,276 m3 of contaminated soils, at CRL. 

Canada’s 7th report also shows major unexplained changes in the inventory of federal radioactive waste relative to Canada’s 6th national report, The absence of adequate explanations for these changes calls into question the 7th report’s credibility.

Comparing data from Table D.8 (p. 48) in Canada’s 7th report to data in the 6th report (Table D.3, p. 27) for CRL, the reported volume of intermediate-level waste (ILW) decreased by 95% – from 19,648 to 1,050 m3.  

A footnote to Table D.8 says:

“Prior estimates were based on a conservative assumption that all waste stored within a structure that could contain ILW would be categorized as ILW until better characterization data became available. Between 2016 and 2019, retrieval and processing operations were conducted on selected legacy wastes in storage, and records were verified to extrapolate the current volumes.” 

Canadian Nuclear Laboratories (CNL), the operator of CRL, is not listed as a contributor to Canada’s 7th report.  Canada’s 7th report should identify the body that did the “better characterization” of ILW, provide details on how it was done, and specify quantities of ILW that were reclassified as low-level waste (LLW).   More generally, clarification is needed as to how the Government of Canada’s ILW and LLW are differentiated. 

The disappearance of 18,598 m3 of ILW at CRL can only be partly accounted for by a 12,873 m3 increase in LLW (comparing Table D.8 in Canada’s 7th report to Table D.3 in the 6th report).  

This apparent reclassification of federal ILW as LLW has implications for a proposed landfill at CRL, listed in section 3.0 of the 7th report as a “current priority”:

a near surface disposal facility (NSDF) for the disposal of up to 1,000,000 m3 of low-level radioactive waste (LLW) at CRL. Pending regulatory approval, the proposed disposal facility will be constructed, and the forecasted date of operations is 2024. 

Although this proposed “NSDF” facility is termed a “near surface disposal facility” in the 7th report, the final Environmental Impact Statement (EIS) for this facility says (p. 1-5) that it “would resemble a conventional landfill for municipal or industrial refuse, with measures to cover the waste.”

According to SSR-5, Disposal of Radioactive Waste, such a landfill facility would be suitable only for disposal of very low level radioactive waste (VLLW) – waste with low concentrations or quantities of radioactive content.  Plans to put LLW – and possibly ILW reclassified as LLW – in such an above-ground, landfill-type mound are a matter of concern.  Again, clarity is needed on how Canada’s wastes are classified.

Note that Canada’s 7th report does not provide data for wastes considered to be VLLW.

The final EIS indicates that CNL intends to put 134,000 m3 of packaged wastes in this proposed disposal facility (Table 3.3.1-1, p. 3-24). The final EIS (p. 3-23) and the NSDF Project Waste Acceptance Criteria (pages 12 and 24) identify as packages intermodal containers (e.g., 20-foot ISO containers), steel waste boxes (e.g., B-25 boxes), drums (e.g., 205-L drums), shielded waste packages, and disused sources.

These packages could contain a variety of long-lived and high-activity radionuclides, possibly not well characterized, and very likely unsuitable for landfill disposal.  

An NSDF Project Reference Inventory Report notes that there are data gaps “compared to what would be required for disposal assessment” of packaged wastes to be put in the facility.  This report describes assumptions, methods, use of scaling factors, qualitative assessments, etc. used to estimate activities of specific radionuclides in the packaged wastes at CRL.  These estimates do not appear in Canada’s 7th report.

Another major change in Canada’s 7th report relative to the 6th report is the 59% decrease in the reported volume of LLW in the form of “Contaminated soils” at Chalk River – from 382,842 m3 in 2017 (Table D.3) to 156,276 m3 in 2020 (Table D.8).  

No explanation is given for this decrease of 226,566 m3 in the reported volume of contaminated soils. The description in Canada’s 7th report of the sources of these contaminated soils — “Luggers, 205 L-steel drums, B-25 containers in SMAGS, sand trenches and above-ground stockpiles” — is identical to that found in the 6th report.

Canada’s reduced inventory of contaminated soils also has implications for wastes to be put in the proposed landfill.  The April 2017 draft EIS for this facility gave a volume figure of 370,000 m3 for “Soil and Soil‐like Waste” (p. 3-8) – similar to the figures of 380,000 m3 of contaminated soils and slags in WMA F found in Table B-2, and 382,842 m3 in the 6th report.  The final EIS has no figure for contaminated soils to be put into the facility – only a combined figure of 866,000 m3 for all types of non-packaged wastes.  

An explanation for the change in contaminated soil volume at CRL between Canada’s 6th and 7th reports is needed. 

Table D.12 and section 8.1 of Canada’s 7th report indicate that CNL was actively decommissioning various facilities (e.g., the waste water evaporator building, NRX delay tanks, NRX fuel bay,  NRX ancillary buildings, plutonium recovery laboratory, plutonium tower) at Chalk River during the April 1, 2017, to March 31, 2020 reporting period.  However, whereas the 6th report had separate tables for wastes from “normal operations” (Table D.3) and wastes from “decommissioning activities” (Table D.5), the latter table was omitted from Canada’s 7th report. 

An explanation is needed as to why a table describing wastes arising from decommissioning activities has been removed from Canada’s 7th report.

Table D.8 (p.49) in Canada’s 7th report has a row labeled “Decommissioning waste” for CRL.  The dates given for this row are January 1, 2005 to December 31, 2016.  This would seem to indicate that data for decommissioning waste for Chalk River in the 7th report were not updated from the 6th report, which shows the same time period.  

However, the two reports have greatly different volumes – 332 m3 ILW and 16,894 m3 LLW in the 7th report; compared to 125 m3 ILW and 2,876 m3 LLW in the 6th report. 

This inconsistency should be addressed.

Of particular concern is the absence of data on activity and specific radionuclides for the Government of Canada’s decommissioning wastes.  GSR Part 6, Decommissioning of Facilities, states that 

During the preparation and updating of the final decommissioning plan, the extent and type of radioactive material at the facility (e.g. activated and contaminated structures and components) shall be determined by means of a detailed characterization survey and on the basis of records collected during the operational period. (p. 16)

Absence of data on activity and specific radionuclides for federal decommissioning wastes in Canada’s 7th report indicates that final decommissioning plans and detailed characterization surveys may not have been done prior to conduct of decommissioning activities.  This would be problematic given that 

With the implementation of the government-owned contractor-operated (GoCo) model at AECL sites, CNL continues to significantly accelerate decommissioning and remediation activities. (Canada’s 7th report, p. 2)

The data shown in Table D.8 in Canada’s 7th report for the Government of Canada’s Whiteshell Laboratories, currently undergoing accelerated decommissioning, differ substantially from those found in the 6th report.

The category of “Research reactor waste and decommissioned reactor waste” for the Whiteshell Laboratories, included in the 6th report, is missing from the 7th report.  Both LLW and ILW at Whiteshell are now labelled as “Decommissioning waste (January 1, 2005, to December 31, 2016).”  

As with the CRL decommissioning waste, this December 31, 2016 date may be an error.  A correction or further explanation is needed.  

Table D.5 in Canada’s 6th report gave volume and activity data for decommissioning wastes at Whiteshell (22 m3 and 148 TBq ILW, 1598 m3 and 6 TBq LLW); Table D.3 in the 6th report gave volume and activity data (863 m3 and 2,794 TBq ILW, 19,700 m3 and 325 TBq LLW) for Whiteshell operations wastes. 

Canada’s 7th report (Table D.8, p. 51) does not provide separate values for Whiteshell decommissioning and operations wastes – both are combined as “Decommissioning waste”.   Activity data for these wastes are now listed as “Not Available”.  

An explanation as to why data on the activity of the Whiteshell wastes were removed from Canada’s 7th report is needed.  As with the CRL decommissioning wastes, lack of activity data for the Whiteshell decommissioning wastes raises concerns that final decommissioning plans and characterization surveys may not have been done before decommissioning activities were carried out.

With regard to the volume of Whiteshell wastes, Table D.8 (p. 51) in Canada’s 7th report provides a figure of 240 m3 of ILW.  This represents only 27% of the 885 m3 of Whiteshell ILW in the 6th report (adding together the separately reported volumes of decommissioning and operations waste).  The 6th report had a footnote stating that “Volumes for ILW/LLW are based on method of storage and do not necessarily represent the actual breakdown of waste into ILW and LLW”.

Canada’s 6th report listed a total of 21,298 m3 of LLW at Whiteshell, including 19,700 m3 of “operations” LLW (in “above-ground concrete bunkers and trenches”) and 1,598 m3 of “decommissioning” LLW (in “above-ground concrete bunkers”).  In Canada’s 7th report, this total volume decreased by 21% to a value of 16,861 m3 of LLW in “above-ground concrete bunkers”.  

Canada’s 7th report gives no explanation for these considerable decreases in the ILW and LLW inventories at Whiteshell.  One possibility is that decommissioning wastes have already been shipped to Chalk River, even though Canada’s 7th report implies that this would not be done until approval was granted for the proposed CRL landfill:

“For the wastes that are currently on-site, CNL is planning to transport certain LLW and other suitable wastes from Whiteshell to CRL for disposal in the proposed NSDF” (p. 297).

The 7th report should explain the 73% decrease in ILW volume and the 21% decrease in LLW volume at the Whiteshell Laboratories. 

Accurate accounting of volumes and activities for the Whiteshell decommissioning wastes is of particular importance, given that the contract between AECL and the consortium of multinational engineering firms includes a special “target cost” agreement that provides bonuses for decommissioning Whiteshell as quickly as possible.  

With regard to Canada’s method of waste classification, the 6th report says:

A definitive numerical boundary between the various categories of radioactive waste – primarily between LLW and ILW – cannot be provided because activity limitations differ between individual radionuclides and radionuclide groups, and will be dependent on short- and long-term safety-management considerations. For example, a contact dose rate of two millisieverts per hour (mSv/h) has been used in some cases to distinguish between LLW and ILW.

A much different waste classification is found in the 7th report:

LLW contains material with radionuclide content above established clearance levels and exemption quantities, but generally has limited amounts of long-lived activity. For orientation purposes only, a limit of 400 Bq/g on average (and up to 4,000 Bq/g for individual waste packages) for long-lived alpha emitting radionuclides can be considered in the classification process. For long-lived beta and/or gamma emitting radionuclides, such as carbon-14, chlorine-36, nickel-63, zirconium-93, niobium-94, technetium-99 and iodine-129, the allowable average activity concentrations can be considerably higher (up to tens of kBq/g) and can be specific to the site and disposal facility. LLW requires isolation and containment for up to a few hundred years.

A similar classification of LLW is found in the NSDF Project Waste Acceptance Criteria (p. 36).  Both resemble the description of LLW in IAEA General Safety Guide GSG-1, Classification of Radioactive Waste. However, neither the new LLW classification in Canada’s 7th report, nor CNL’s LLW classification for its “NSDF”, would appear to identify wastes suitable for disposal in a landfill-type facility.  

As noted earlier, landfill-type facilities are suitable for disposal only Very Low Level Waste (VLLW) – typically, soil and rubble with low levels of radioactivity and very limited concentrations of longer lived radionuclides.  Past activities at CRL related to extraction of isotopes from irradiated fuels and targets (e.g., the plutonium recovery facility, the plutonium tower, the waste water evaporator, the nitrate plant, the thorium pit, the molybdenum-99 processing facility), have left a legacy of long-lived wastes that almost certainly will require management as ILW.

After AECL contracted a consortium of multinational engineering firms to operate the Government of Canada’s nuclear sites in 2015, Canada’s Parliament greatly increased annual appropriations to AECL for decommissioning and waste management. With this increased funding for accelerated decommissioning, and plans for three new disposal facilities for the Government of Canada’s wastes (the CRL landfill, and entombment of the NPD and WR-1 reactors), clear, transparent,  accurate and up-to-date data on federal radioactive wastes should be a high priority for Canada.

Although Canada’s 7th report claims (p. 189) that “Since the Sixth Review Meeting, significant progress has been made in developing and implementing long-term solutions for L&ILW at AECL sites which will address more than half of Canada’s inventory of these waste types,” this claim is not supported by evidence.  Although the Annex of the report describes CRL waste management areas A, B, C, D, E, F, G, H, and J; the Liquid dispersal area; Acid, chemical and solvent pits; Waste tank farm; Ammonium nitrate decomposition plant; and Thorium nitrate pit; it does not indicate that “long-term solutions” have been developed for radioactive wastes in any of these areas.

In summary, Canada’s 7th report could be revised to 

  • include all available data on activity and specific radionuclides for the Government of Canada’s radioactive wastes stored at CRL and Whiteshell;
  • explain the changes  in data for ILW, LLW, and contaminated soils at CRL  and Whiteshell in the 7th report relative to the 6th report, including information on the “better characterization” of ILW;
  • explain why data for wastes arising from decommissioning activities at Chalk River and Whiteshell are shown as not having been updated since 2017;
  • clarify whether final decommissioning plans and detailed characterization surveys were completed prior to conduct of accelerated decommissioning activities at CRL and Whiteshell;
  • explain why the separate table of wastes arising from decommissioning activities found in the 6th report was removed from the 7th report; 
  • clarify that the proposed “NSDF” at CRL would resemble a municipal landfill; and
  • provide evidence that long-term solutions have been developed for remediation of the CRL waste management  areas.

Addressing these issues would add rigour and credibility to Canada’s 7th report. 

We hope this note can stimulate discussions during the Seventh Review Meeting

Thank you for your attention to this matter.

Best regards,

Ole Hendrickson, Ph.D. (ole@nrtco.net)

Researcher, Concerned Citizens of Renfrew County and Area

cc:  cnsc.info.ccsn@canada.ca

Table B-2 Summary of Waste Management Areas at CRL and Estimates of Waste Volumes and Radioactivity Content 

Source: Chalk River Laboratories Comprehensive Preliminary Decommissioning Plan, CPDP-508300-PDP-001, Revision 2, March 2014 

AreaPeriod of OperationDescriptionWaste Volume (m3)
Major Activity (1)Notes
Designation

SolidLiquidTypeTBq
Waste Management Area A
Liquid Wastes
Various drummed and bottled liquids emptied into below-grade concrete structures.n.a.33N/AN/ALimited records for drummed and bottled liquids buried prior to 1956
Solid Wastes1946-1955Liquid wastes discharged into trenches in 1953 (4,500 m3), 1954 September (7.2 m3) and 1955 February (50 m3) resulting in contaminated soil. Solid wastes emplaced in unlined trenches and a variety of “special burials”, such as the NRX calandria.21,200Misc. liquids
Mixed FPN/ALimited records for solid wastes buried prior to 1955. Source of a groundwater plume.
Liquid Dispersal Area
Reactor Pit #11953-1998Liquid waste discharged to natural depression between 1953 and 1956 resulting in contaminated soil. Lightly contaminated equipment and suspect soils later used to fill depression.7,100n.a.β/γ α
100 0.1
Estimated disposal of 74 TBq 90Sr plus 100 g (Pu equivalent) of alpha-emitters. Source of a groundwater plume.
Laundry Pit1956-1957Aqueous waste from Decontamination Centre and Laundry discharged to engineered pit resulting in contaminated soil. 4,000n.a.β/γ α0.06 0.0003Small inventory compared with other LDA pits. 
Chemical Pit1956-1995Liquid aqueous waste from site labs and chemical operations discharged to a gravel-filled pit resulting in contaminated soil.17,700n.a.β/γ α  Tritium230 0.4 70Source of a groundwater 90Sr plume. Groundwater from Chemical Pit plume is subject of pump and treat program.
Reactor Pit #21956-2000Lightly contaminated water from Rod Storage Bays, and NRX & NRU operations resulting in contaminated soil.28,200n.a.β/γ α Tritium500 0.5 1,000Source of a groundwater plume.
Waste Management Area B
Sand Trenches1953-1963Solid wastes in unlined trenches covered with sand: Intermediate Level Radioactive Waste (ILW) emplaced prior to 1956 August, only Low Level Waste (LLW) emplaced after 1956 September.~9,000Misc. bottled liquidsMixed LLW and ILW
~75Use discontinued in favour of engineered structures. Limited inventory data. Source of two separate groundwater plumes.
Asphalt-lined trenches
1955-1959Intermediate-level solid wastes, i.e., wastes having external fields >100 mR/h at 30 cm, that were emplaced in asphalt-lined and –capped trenches1,600Misc. bottled liquidsILWN/AEstimated to contain 0.6 TBq of 239Pu.
Rectangular Concrete bunkers1959-1979Low level solid wastes in rectangular concrete bunkers. (Below grade but above the water table)8,500ResidualLLWA
Special burials1955-1973Various materials including the NRU and the second NRX calandrias.914*220*

Estimates are available for individual burials.
Circular concrete bunkers1979 – presentLow level solid wastes. (Below grade but above the water table)
6,850ResidualLLWA

Tile Holes – Nuclear Reactor Fuels1956 – presentReactor fuel high-level wastes in vertical, below-grade facilities.
120n.a.Used FuelAEstimates available for fissile material quantities. Fuel-bearing structures are the subject of a remediation program. Certain HEU fuels are candidates for return to U.S.
Tile Holes – 99Mo wastes1970 -presentHigh-level wastes from 99Mo production200n.a.ILWN/AEstimates available for fissile material quantities.
Tile Holes – other wastes1956 -presentA variety of high level wastes including reactor components.950n.a.ILWN/ACell wastes, reactor components, Rod Bay wastes.
Waste Management Area C
C Extension1993-2006Low level solid waste (external fields <100 mR/h at 30 cm) in unlined trenches. Higher proportion of drummed waste than Area C.9,000ResidualLLWACharacterization data available for some radionuclide inventories. Source of groundwater plume.
Sand Trenches1963-2006Low-level solid waste (external fields <100 mR/h at 30 cm) in unlined trenches. Total area is approx. 4.5 ha; impermeable cover installed on entire area in 2013. Waste is half from CRL and half from across Canada including NPD.100,000Drummed & bottled liquids
LLWN/ALimited characterization data for inventories. Source of a groundwater plume.
AreaPeriod of OperationDescriptionWaste Volume (m3)
Major Activity (1)Notes
Designation

SolidLiquidTypeTBq
Waste Management Area D1976 – presentFenced gravel compound used for aboveground storage of potentially contaminated equipment, materials and drummed liquids. Not a burial site. A Mixed Waste Facility used for temporary storage, sampling and bulking is also in WMA D.760 (LLW)
LLWASmall numbers of transient drums may be stored at any particular time. The drummed liquids (lightly contaminated aqueous wastes and waste oils) are stored in marine containers.
Acid, Chemical and Solvent Pits1982-1987Small fenced compound containing three small pits, which as the names imply were used for different non-active liquid wastes and very small quantities of solid wastes.Acid: minorAcid: 11.2 Chem.: 2.7 Sol.:  5.3


Acid: Hydrochloric, Sulphuric, Nitric, Chromic acids, potassium carbonate powder, citric powder and acid batteries. Chemical: Scintillation fluids, Alconox and other cleaning agents, ammonia, alkylating agents, others. Solvent: Mixed solvents, oils, scintillation solutions, ammonia, varsol, acetone, others.
Waste Management Area E1977-1984Used for disposition of lightly contaminated & suspect bulk materials (building debris and soils) from the CRL Controlled Area.N/An.a.Suspect slightly contaminatedN/AThe volume of suspect contaminated materials is believed to be a small fraction of the total volume of materials stored here.
Tank Farm1961-1968Tank Farm with intermediate to high-level wastes in tanks in concrete vaults with leak-detection systems  Intermediate – T-40F (secondary concrete containment), T-40E (empty), T-40D (concrete pad) High level – T-283A, B, C, D (all with secondary concrete containment)n.a.68β/γ α
150Monitoring & surveillance confirms containment of these wastes and the facility includes emergency transfer lines.
Waste Management Area F1976-1979Contaminated soils and slags from Port Hope, Albion Hills, Mono Mills and Ottawa stored above the water table in sand valley. Unsuccessful clay cover.~380,000zeroRadium0.5Approx. 515 GBq Total 226Ra,  4 – 13 Mg Arsenic,  80 Mg U.
Waste Management Area G1989-presentNPD spent fuel dry storage facility – aboveground concrete canisters.
4,921 (bundles)
zeroIrrad. UAComplete inventory data available. Monitoring & surveillance confirms containment within structures.
Waste Management Area H (MAGS and SMAGS)2001-presentPrefabricated metal and concrete storage buildings with capability of storing 865 m3and approximately 4,000 m3 each, respectively, of compacted LLW in B-1000 compactor boxes, 45-gallon drums (204 liters), wooden crates, boxes and B-25 containers. Bulk materials and NRX stack pieces are also stored in WMA H.9,000n.aMixed FPN/AAll waste will be removed by Operations prior to turnover to Decommissioning. Some residual contamination may be present as a result of operational activities.
WMA J Bulk Material Landfill (BML)2010–presentEngineered landfill used for the storage of sewage sludge for the CRL sewage treatment plant1,600n.a.Mixed FP
~10-4
Leachate is transferred to the sewage treatment plant.
Nitrate Plant1953-1954Discharges of mixed fission products in salt solutions to limed pit following a process accident. Decontaminating solutions also released. Contaminated rubble from Building 233 demolition.
3,400n.a.β/γ60Estimated 60 TBq of β/γ activity (35% 90Sr) in liquid releases – small α inventories. Plant demolished and buried on-site, no data for solid waste inventories.
.Thorium Pit1955-1960Reprocessing wastes from operation of the 233U extraction facility.
150n.a.Nat. Th, 233U and mixed FPAApproximate total of 45 m3 reprocessing solution discharged in separate dispersals to crib containing ammonium carbonate (~4,000 kg of nat. Th, 27 g 233U).
Above Ground Buildings and Structures in Waste Management Areas
Buildings and Structures in WMAs1953 – presentVarious buildings/gatehousesN/An.a.N/AN/A

(1) Activity at time of emplacement – not corrected for decay N/A = no quantitative data available n.a. = not applicable A = quantitative data available 

Reforms needed at Canadian Nuclear Safety Commission ~ Hill Times letter to the editor

April 12, 2021

https://www.hilltimes.com/2021/04/12/reforms-needed-at-canadian-nuclear-safety-commission/292381

(en français ici)

Canada’s nuclear regulatory agency, the Canadian Nuclear Safety Commission says it’s the “World’s best nuclear regulator” on its website. That “self-image” of the CNSC’s is inconsistent with statements made in recent years by international peer reviewers, high-ranking Canadian officials, international nuclear proponents and others.

The International Atomic Energy Agency recently reviewed Canada’s nuclear safety framework. It identified numerous serious deficiencies including: not following IAEA guidance on nuclear reactor decommissioning, failure to justify practices involving radiation sources, inadequate management systems for transporting nuclear materials and allowing pregnant nuclear workers four times higher radiation exposures than IAEA would permit.


In testimony before the House Standing Committee on Natural Resources, in November 2016, Canada’s Environment Commissioner said:

“the Canadian Nuclear Safety Commission… was quite difficult to work with… I would say that the commission was aggressive with the auditors.”

In April 2017, the Expert Panel on reform of environmental assessment, in its final report noted that it had heard many concerns about lack of independence at the CNSC:

“There were concerns that these Responsible Authorities (CNSC and NEB) promote the projects they are tasked with regulating…The term “regulatory capture” was often used when participants described their perceptions of these two entities.”

Counter to Expert Panel recommendations, the CNSC is the agency responsible for making environmental assessment and licensing decisions for three controversial radioactive waste disposal projects on the Ottawa and Winnipeg rivers. 


The nuclear industry publication, Nuclear Energy Insider, recently touted Canada’s “benign regulatory environment” as a reason for SMR developers to come to Canada to experiment with and promote “small”, “modular”, nuclear reactors.


Globe and Mail article in November 2018, revealed that CNSC officials had engaged in backroom lobbying to exempt small modular nuclear reactors from environmental assessment. 


A June 2020 briefing session for MPs and media,“Sham regulation of radioactive waste in Canada,” by the Canadian Environmental Law Association and other NGOs, outlined several ways in which the CNSC was creating “pseudo regulations” to benefit the nuclear industry and allow cheap and ineffective nuclear waste facilities to receive approval and licensing.

A recent petition to the Auditor General from our respective public interest citizens’ groups and Quebec colleagues, entitled “Nuclear governance problems in Canada,” noted that the CNSC has a mandate to protect health but lacks a health department.  A review of CNSC’s organizational chart reveals that the word health does not appear on it.


We believe the CNSC is in need of serious reform if Canadians want it to become a world-class nuclear regulator that prioritizes the health of Canadians and the environment over the health of the nuclear industry. The Government of Canada should address regulatory capture and other serious problems at the CNSC as soon as possible.

Lynn Jones, MHSc, Ottawa, Ontario, Concerned Citizens of Renfrew County and Area

Anne Lindsey, OM, MA, Winnipeg, Manitoba, Concerned Citizens of Manitoba

~~~~~

The images below are screen shots from the CNSC website, on April 13, 2021, illustrating that the word “health” does not appear on the organizational chart, despite the fact that CNSC’s primary legal mandate is to protect the health of Canadians from the adverse effects of exposure to ionizing radiation.

CNSC president should not report to the Minister of Natural Resources, according to IAEA guidance

Having the CNSC report through the Minister of Natural Resources who is charged with producing (and promoting) nuclear energy under the Nuclear Energy Act is not consistent with the IAEA’s guidance on “independence”.  


IAEA General Safety Guide No. GSG-12, Organization, Management and Staffing of the Regulatory Body for Safety says:

2.3  …the credibility of the regulatory body with the general public depends on whether the regulatory body is regarded as being independent from the organizations it regulates, as well as independent from other government agencies or industry groups that promote nuclear technologies.

The IAEA recommends that the CNSC’s independence from Parliament and government not be absolute:

2.6. Paragraph 2.8 of GSR Part 1 (Rev. 1) [2] states that:“To be effectively independent from undue influences on its decision making, the regulatory body: …Shall be free from any pressures associated with political circumstances or economic conditions, or pressures from government departments, authorized parties or other organizations”.  

2.7. The regulatory body should, however, be accountable to the government and to the general public with regard to effectively and efficiently fulfilling its mission to protect workers, the public and the environment…

More specifically, it is unacceptable that the CNSC’s funding requests come through the Minister of Natural Resources:

2.14. …Review and approval of the regulatory body’s budget should be performed only by governmental agencies that are effectively neutral in respect of the development, promotion or operation of facilities and conduct of activities. Such an approach provides additional assurance of the independence of the regulatory body 

Under the Nuclear Energy Act, the Minister of Natural Resources is Canada’s promoter of nuclear technologies:

Powers of Minister 10(1) The Minister may

(a) undertake or cause to be undertaken research and investigations with respect to nuclear energy;

(b) with the approval of the Governor in Council, utilize, cause to be utilized and prepare for the utilization of nuclear energy;

(c) with the approval of the Governor in Council, lease or, by purchase, requisition or expropriation, acquire or cause to be acquired nuclear substances and any mines, deposits or claims of nuclear substances and patent rights or certificates of supplementary protection issued under the Patent Act relating to nuclear energy and any works or property for production or preparation for production of, or for research or investigations with respect to, nuclear energy



The President of Canada’s nuclear regulatory body (CNSC) reports to the Minister of Natural Resources.  The Nuclear Safety and Control Act says

12(4) …the President shall make such reports to the Minister as the Minister may require concerning the general administration and management of the affairs of the Commission…

Hence, the Minister in charge of nuclear energy, including federal (AECL) properties for production and research of nuclear energy, is also in charge of the regulatory body that is supposed to protect workers, the public and the environment. 

 
This creates a lack of independence of the regulatory body. 

 
The Nuclear Safety and Control Act does allow for the President of the CNSC to report to a minister other than the Minister of Natural Resources.  From section 2, Definitions:

Minister means the Minister of Natural Resources or such member of the Queen’s Privy Council for Canada as the Governor in Council may designate as the Minister for the purposes of this Act.


A quick and cheap fix to CNSC’s lack of independence would be to designate the Minister of Environment and Climate Change as the “the Minister for the purposes of this Act”. 

 
That being said, both the Nuclear Safety and Control Act and the Nuclear Energy Act are more than 23 years old and have never been reviewed by Parliament.  Such a review is long overdue.

CNSC says climate change is not relevant to environmental assessment of SMRs

Canada’s first formal license application for an SMR is the “Micro Modular Reactor” in Chalk River.

CCRCA, and many others provided written interventions to the CNSC on “the scope of an environmental assessment for the proposed Micro Modular Reactor Project at the Chalk River Laboratories” prior to the one-person “Panel of Commission: R. Velshi, President” that rendered its decision on July 26th.

The CCRCA submission noted, in particular, that under the Impact Assessment Act, the proponent would be required to include as a “factor” in the EA ““the extent to which the effects of the designated project hinder or contribute to the Government of Canada’s ability to meet its environmental obligations and its commitments in respect of climate change.”

We added, “the CNSC has proposed that proponents assess the total GHG production as part of CNSC-led environmental assessments” in its fact sheet entitled “Greenhouse gas emission assessments for the Canadian nuclear fuel cycle,”  

The full CCRCA submission is available here.

Somehow, the Record of Decision on the project scope omits any mention of climate change.  

The CNSC’s decision on the scope of the MMR project indicates that climate change is not a relevant factor in the consideration of environmental impact of SMRs.

Here’s our take-away:

  • Reducing GHG emissions is a government priority.  This is reflected in the Impact Assessment Act.  The Minister of Natural Resources says nuclear power is essential to reduce GHGs (no path to net zero without nuclear) 
  • The CNSC did not include GHG emissions as a factor in assessing its first SMR license application – even when requested to do so – and even when its own “interim strategy for environmental assessments” calls for this.
  • The CNSC should not lead environmental assessments of nuclear reactors, including SMRs. 
  • The Physical Activities Regulations under the Impact Assessment Act should be changed to remove exemptions for new nuclear reactors.
Global Warming vs. Climate Change | Resources – Climate Change: Vital Signs  of the Planet

Don’t approve Nuclear Waste regulations which put Canadians at risk, says NDP Natural Resources Critic Richard Cannings

Office of/Bureau du Richard Cannings MP South Okanagan – West Kootenay

June 17, 2020

South Okanagan MP Richard Cannings has self-isolated after ...

Don’t approve Nuclear Waste regulations which put Canadians at risk,
says NDP Natural Resources Critic Richard Cannings

The Canadian Nuclear Safety Commission (CNSC) should not approve a suite of regulatory documents on radioactive waste at its meeting June 18, 2020 and instead live up to the Liberal government’s commitment to openness and transparency for regulatory development. Some of these regulations developed by commission staff are at best vague guidelines that leave nuclear waste policy decisions in the hands of private industry, instead of actually prescribing actions that are in the public interest.

These regulatory changes would pave the way for several controversial nuclear waste disposal projects, including a giant mound at Chalk River, Ontario, two entombments of shut- down reactors, and a proposed deep geological repository for the burial of high-level nuclear fuel waste.

This proposal does not meet Canada’s commitment to meeting or surpassing international standards for the handling of nuclear waste. For example, the entombment of nuclear reactors is designated as “in-situ decommissioning”, a practice that the International Atomic Energy Agency says should only be used as a last option for facilities damaged in accidents.

Of further concern is the lack of clarity in the proposed regulations. In many cases the licensee is directed to develop safety requirements with no explicit directions as to what those safety requirements are. The giant mound at Chalk River is meant to contain up to 1 million cubic metres of low- to intermediate-activity nuclear waste but these activity levels are not defined and the private owner of the facility would get to decide what materials are stored in that mound of nuclear waste.

The Minister of Natural Resources has committed to consulting Canadians on a policy framework and strategy for radioactive waste. Instead we have this backdoor process with limited public input and no parliamentary oversight. The minister should be conducting a public process to develop a Canadian framework for radioactive waste management that meets or exceeds international best practices, a framework that does not allow the nuclear industry to police itself.